Work continues on the second phase of the ³¬¼¶µõÖÓÄÌ’s Education 2020 Capital Project, which was approved by voters in March 2022, and reauthorized in May 2023.
Work on the retention pond behind the Morgan Road Complex was paused due to oversaturation from the recent heavy rains. Contractors are working on a solution.
Work continues on preparing the stadium grounds for the installation of new turf, and the southern area of the stadium continues to be graded for paving. The plan is to have the stadium completely prepared for turf installation by the end of the week, with paving starting as well.